How to make a rotating shift pattern for your crews
If you run a site that never closes, the rotation is the part of your job everyone notices. Get it right and every shift is covered without anyone working more than their share. This guide takes the decisions in order: shift length, how many crews you need, which pattern, how far apart each crew starts, and how to get the finished rota onto every phone and the break-room wall.
Step 1: count the hours you need to cover
Start with the clock, not the people. A site that runs around the clock needs 168 hours of cover a week for every position on shift. If two operators must be on at all times, you are filling two seats of 168 hours each. Write down how many people each shift needs first, because every later number scales with it.
Step 2: pick a shift length and see how many crews it takes
When one crew covers each shift, each crew averages 168 hours divided by the number of crews: 42 hours a week with four crews, 56 with three. That is why almost every 12-hour and 8-hour rotation uses four crews, while 24-hour fire and EMS rotations use three or four.
| Shift length | Shifts a day | Crews | Average hours a week | Patterns |
|---|---|---|---|---|
| 8 hours | 3 | 4 | 42 | Continental |
| 12 hours | 2 | 4 | 42 | DuPont, Pitman, 2-2-3, 4 on 4 off, 2 days 2 nights 4 off |
| 24 hours | 1 | 3 | 56 | 24/48, 48/96, Kelly |
| 24 hours | 1 | 4 | 42 | 24/72 |
Each crew works a share of the days: three days in four on the 8-hour continental rotation, one day in two on a 12-hour rotation, one day in three on 24/48. Divide the shifts a day by that share and you get the number of crews, so you can check any pattern someone suggests.
Step 3: choose the pattern
Once the crew count is settled, the choice is about how the work falls for each person. Put these questions to your crews before you decide. Every pattern page shows a full 2027 calendar for each crew.
- Same shift or switching? On Pitman and 4 on 4 off two crews keep days and two keep nights. On DuPont and 2-2-3 rotating everyone shares the nights.
- Long breaks or short runs? DuPont gives 7 days off in a row every 28 days, with a hard week before it. 2 days, 2 nights, 4 off never runs more than 4 shifts and gives 4 days off every 8 days.
- Shorter shifts? The continental rotation keeps 8-hour shifts and moves each crew forward from days to evenings to nights.
- 24-hour duty? 24/48, 48/96 and the Kelly rotation use three platoons, and 24/72 uses four.
For a closer look, compare DuPont, Pitman and 2-2-3, 4 on 4 off and continental or 24/48, 48/96 and Kelly.
Step 4: stagger the crews
On most rotations every crew works exactly the same sequence and only starts on a different day. Space the crews evenly: divide the number of days before the pattern repeats by the number of crews. On DuPont that is 28 days for 4 crews, so crew B starts 7 days after crew A, crew C 7 days after crew B, and crew D 7 days after crew C. Get the spacing wrong and you will find days with two night crews and nobody on days.
| Pattern | Repeats every | Crews | Days between crews |
|---|---|---|---|
| DuPont | 28 days | 4 | 7 |
| 2-2-3 rotating | 28 days | 4 | 7 |
| Continental | 28 days | 4 | 7 |
| 2 days, 2 nights, 4 off | 8 days | 4 | 2 |
| 24/48 | 3 days | 3 | 1 |
| 48/96 | 6 days | 3 | 2 |
| Kelly | 9 days | 3 | 3 |
| 24/72 | 4 days | 4 | 1 |
With that spacing every day has exactly one crew on each shift, and the work is shared evenly: over time every crew gets the same nights, weekends and long breaks, just in different weeks. Here is DuPont with all four crews, day 1 on Monday 4 January 2027. D is a day shift, N a night shift, and a blank square a day off.
| Mon | Tue | Wed | Thu | Fri | Sat | Sun | |
|---|---|---|---|---|---|---|---|
| Week 1 | |||||||
| A | Night shift | Night shift | Night shift | Night shift | Off | Off | Off |
| B | Off | Off | Off | Off | Off | Off | Off |
| C | Off | Off | Off | Day shift | Day shift | Day shift | Day shift |
| D | Day shift | Day shift | Day shift | Off | Night shift | Night shift | Night shift |
| Week 2 | |||||||
| A | Day shift | Day shift | Day shift | Off | Night shift | Night shift | Night shift |
| B | Night shift | Night shift | Night shift | Night shift | Off | Off | Off |
| C | Off | Off | Off | Off | Off | Off | Off |
| D | Off | Off | Off | Day shift | Day shift | Day shift | Day shift |
| Week 3 | |||||||
| A | Off | Off | Off | Day shift | Day shift | Day shift | Day shift |
| B | Day shift | Day shift | Day shift | Off | Night shift | Night shift | Night shift |
| C | Night shift | Night shift | Night shift | Night shift | Off | Off | Off |
| D | Off | Off | Off | Off | Off | Off | Off |
| Week 4 | |||||||
| A | Off | Off | Off | Off | Off | Off | Off |
| B | Off | Off | Off | Day shift | Day shift | Day shift | Day shift |
| C | Day shift | Day shift | Day shift | Off | Night shift | Night shift | Night shift |
| D | Night shift | Night shift | Night shift | Night shift | Off | Off | Off |
Pitman and 4 on 4 off work differently. There a day crew and a night crew are on the same dates, one on days and one on nights, so there is no single spacing. Use the crew table on the pattern page instead.
Step 5: check one crew’s row against fatigue guidance
Researchers do not agree on one best rotation, but the guidelines NIOSH collects for rota design give a few checks worth making. Read one crew’s row with them in mind:
- Keep runs of night shifts short on a rotating shift pattern.
- Rotate forward, from days to evenings to nights, rather than backward.
- Leave at least 11 hours between the end of one shift and the start of the next.
- Consider two days off after three 12-hour shifts in a row.
- Avoid starts at 6 a.m. or earlier where you can, and give every crew some weekends off.
No pattern passes every check. DuPont, for example, has 4 nights in a row and only 1 day off after one run of day shifts, in exchange for its week off. Choose knowingly, and tell your crews why you chose it.
Step 6: pick the start date
Choose the date crew A works day 1, and every other crew follows from it. Look at the first months before you fix it: which crew has its week off over a holiday or a planned shutdown depends only on this date. Moving the start by a whole repeat changes nothing, so only the position inside the repeat matters.
Step 7: share the rota with your crews
A rotation only works when everyone can see their own days. MyShiftPlan does this for free, with no accounts:
- Open the planner and choose the pattern.
- Under “Who is this calendar for?” pick “My whole team (Team A, B, C…)”. For the patterns in the table above, the planner fills in the number of teams and the days between them. Check them against your plan.
- Answer “Which day of the cycle are you on today?” for Team A, then switch to “All teams” to see that every shift is covered.
- Open the ⋮ menu and choose “Share with my team”, then post the link in the crew chat. Each person opens it, picks their team and saves it in their own browser. The link carries only the pattern, Team A’s date and the team spacing, never names, notes or shift times.
- Choose “Download PDF” for a printout with every team side by side to pin up on site. The QR code in its footer opens the pattern’s page.